PMP · Question 100 · Task 9: Integrate project planning activities
A project manager is leading a project to implement a new software system. The project is using a hybrid approach. The development team is Agile, but the deployment team is Waterfall. The deployment team requires a detailed deployment plan 3 months in advance. The Agile team says they can't provide it. What should the PM do?
A project manager is leading a project to implement a new software system. The project is using a hybrid approach. The development team is Agile, but the deployment team is Waterfall. The deployment team requires a detailed deployment plan 3 months in advance. The Agile team says they can't provide it. What should the PM do?
Answer options:
A.
Force the Agile team to plan 3 months out.
B.
Work with both teams to define a 'Release Train' or synchronization point where the Agile team commits to a specific feature set for the deployment window.
C.
Tell the deployment team to become Agile.
D.
Delay the deployment.
How to approach this question
Hybrid Clash -> Synchronization/Cadence.
Full Answer
B.Work with both teams to define a 'Release Train' or synchronization point where the Agile team commits to a specific feature set for the deployment window.✓ Correct
B
Task 9 (Integration) and Task 13 (Methodology). Managing the interface between Agile and Waterfall requires synchronization points (Releases).
Common mistakes
Trying to change the other team's methodology instead of managing the interface.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert