Hard1 markMultiple Choice

PMP · Question 100 · Task 9: Integrate project planning activities

A project manager is leading a project to implement a new software system. The project is using a hybrid approach. The development team is Agile, but the deployment team is Waterfall. The deployment team requires a detailed deployment plan 3 months in advance. The Agile team says they can't provide it. What should the PM do?

Answer options:

A.

Force the Agile team to plan 3 months out.

B.

Work with both teams to define a 'Release Train' or synchronization point where the Agile team commits to a specific feature set for the deployment window.

C.

Tell the deployment team to become Agile.

D.

Delay the deployment.

How to approach this question

Hybrid Clash -> Synchronization/Cadence.

Full Answer

B.Work with both teams to define a 'Release Train' or synchronization point where the Agile team commits to a specific feature set for the deployment window.✓ Correct
B
Task 9 (Integration) and Task 13 (Methodology). Managing the interface between Agile and Waterfall requires synchronization points (Releases).

Common mistakes

Trying to change the other team's methodology instead of managing the interface.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading