PMP · Question 100 · Task 9: Integrate project planning activities
A project manager is leading a project to implement a new software system. The project is using a hybrid approach. The development team is Agile, but the deployment team is Waterfall. The deployment team requires a detailed deployment plan 3 months in advance. The Agile team says they can't provide it. What should the PM do?
Answer options:
Force the Agile team to plan 3 months out.
Work with both teams to define a 'Release Train' or synchronization point where the Agile team commits to a specific feature set for the deployment window.
Tell the deployment team to become Agile.
Delay the deployment.
114 questions · hints · full answers · grading