PMP · Question 99 · Task 8: Plan and manage scope

A project manager is leading a project to build a new website. The project is using Agile. The team is estimating the user stories. One story is 'As a user, I want to search for products.' The team estimates it at 100 points. The average velocity is 20. What should the PM suggest?

Answer options:

A.

Accept the estimate and plan for it to take 5 sprints.

B.

Tell the team to lower the estimate.

C.

Suggest splitting the story into smaller, more manageable stories (Decomposition/Slicing).

D.

Remove the story.

How to approach this question

Huge Estimate -> Split it.

Full Answer

C.Suggest splitting the story into smaller, more manageable stories (Decomposition/Slicing).✓ Correct
C
Task 8 (Scope). Agile relies on small batch sizes. A story that is 5x velocity is an Epic and must be decomposed to be manageable and reduce risk.

Common mistakes

Accepting 'Epics' into a sprint.