PMP · Question 98 · Task 1: Plan and manage project compliance
A project manager is leading a project to develop a new medical device. The project is subject to FDA regulations. The PM wants to ensure that the project team is aware of the compliance requirements. What should the PM do?
A project manager is leading a project to develop a new medical device. The project is subject to FDA regulations. The PM wants to ensure that the project team is aware of the compliance requirements. What should the PM do?
Answer options:
A.
Email the regulations to the team.
B.
Include compliance training in the project plan and discuss requirements during the kickoff and regular meetings.
C.
Assume the team knows the rules since they are experts.
D.
Hire a compliance officer to do the work.
How to approach this question
Compliance = Training + Communication.
Full Answer
B.Include compliance training in the project plan and discuss requirements during the kickoff and regular meetings.✓ Correct
B
Task 1 (Compliance) and Task 5 (Training). Compliance is a team sport. The PM ensures the team has the knowledge to be compliant.
Common mistakes
Assuming experts know all the specific regulations for this project.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert