For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 97
    Hard1 markMultiple Choice
    Task 9: Integrate project planning activitiesProcessEVMData Analysis

    PMP · Question 97 · Task 9: Integrate project planning activities

    A project manager is leading a project to build a new office. The project is using a predictive lifecycle. The PM wants to ensure that the project is on track. The PM calculates the Critical Ratio (CR). CR = CPI * SPI. The CR is 1.1. What does this mean?

    Answer options:

    A.

    The project is performing well overall.

    B.

    The project is in trouble.

    C.

    The project is exactly on plan.

    D.

    The project is over budget.

    How to approach this question

    Critical Ratio = CPI * SPI. >1 Good. <1 Bad.

    Full Answer

    A.The project is performing well overall.✓ Correct
    Task 5 (Budget) and Task 6 (Schedule). Critical Ratio is a composite index. It helps identify if good performance in one area is offsetting bad performance in another, or if both are good.

    Common mistakes

    Not knowing the CR formula.
    Question 96All questionsQuestion 98

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →