Hard1 markMultiple Choice
PMP · Question 97 · Task 9: Integrate project planning activities
A project manager is leading a project to build a new office. The project is using a predictive lifecycle. The PM wants to ensure that the project is on track. The PM calculates the Critical Ratio (CR). CR = CPI * SPI. The CR is 1.1. What does this mean?
A project manager is leading a project to build a new office. The project is using a predictive lifecycle. The PM wants to ensure that the project is on track. The PM calculates the Critical Ratio (CR). CR = CPI * SPI. The CR is 1.1. What does this mean?
Answer options:
A.
The project is performing well overall.
B.
The project is in trouble.
C.
The project is exactly on plan.
D.
The project is over budget.
How to approach this question
Critical Ratio = CPI * SPI. >1 Good. <1 Bad.
Full Answer
A.The project is performing well overall.✓ Correct
A
Task 5 (Budget) and Task 6 (Schedule). Critical Ratio is a composite index. It helps identify if good performance in one area is offsetting bad performance in another, or if both are good.
Common mistakes
Not knowing the CR formula.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard