PMP · Question 97 · Task 9: Integrate project planning activities
A project manager is leading a project to build a new office. The project is using a predictive lifecycle. The PM wants to ensure that the project is on track. The PM calculates the Critical Ratio (CR). CR = CPI * SPI. The CR is 1.1. What does this mean?
Answer options:
The project is performing well overall.
The project is in trouble.
The project is exactly on plan.
The project is over budget.