    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefitsBusiness EnvironmentValueMetrics

    PMP · Question 104 · Task 2: Evaluate and deliver project benefits

    A project manager is leading a project to develop a new mobile app. The team is using Agile. The PM wants to ensure that the team is delivering value to the customer. Which metric is BEST?

    Answer options:

    A.

    Velocity

    B.

    Lines of Code

    C.

    Customer Satisfaction (NPS) or Usage Metrics of released features.

    D.

    Hours worked

    How to approach this question

    Value = Outcome. Speed = Output.

    Full Answer

    C.Customer Satisfaction (NPS) or Usage Metrics of released features.✓ Correct
    Task 1 (Value). Velocity is useful for planning, but it doesn't measure success. Value is measured by customer behavior/sentiment.

    Common mistakes

    Confusing Velocity with Value.
    Question 103All questionsQuestion 105

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard