Hard1 markMultiple Choice
PMP · Question 104 · Task 2: Evaluate and deliver project benefits
A project manager is leading a project to develop a new mobile app. The team is using Agile. The PM wants to ensure that the team is delivering value to the customer. Which metric is BEST?
A project manager is leading a project to develop a new mobile app. The team is using Agile. The PM wants to ensure that the team is delivering value to the customer. Which metric is BEST?
Answer options:
A.
Velocity
B.
Lines of Code
C.
Customer Satisfaction (NPS) or Usage Metrics of released features.
D.
Hours worked
How to approach this question
Value = Outcome. Speed = Output.
Full Answer
C.Customer Satisfaction (NPS) or Usage Metrics of released features.✓ Correct
C
Task 1 (Value). Velocity is useful for planning, but it doesn't measure success. Value is measured by customer behavior/sentiment.
Common mistakes
Confusing Velocity with Value.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert