PMP · Question 105 · Task 1: Plan and manage project compliance
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is safe. The PM conducts a 'Safety Audit'. What is this?
Answer options:
A plan to be safe.
A structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.
A check of the product.
A risk analysis.