    PracticePMI PMP®PMI PMP Practice ExamQuestion 105
    Medium1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentComplianceQuality

    PMP · Question 105 · Task 1: Plan and manage project compliance

    A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is safe. The PM conducts a 'Safety Audit'. What is this?

    Answer options:

    A.

    A plan to be safe.

    B.

    A structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.

    C.

    A check of the product.

    D.

    A risk analysis.

    How to approach this question

    Audit = Process Check.

    Full Answer

    B.A structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.✓ Correct
    B
    Task 1 (Compliance) and Task 7 (Quality). Audits check the *process* (Quality Assurance), while Inspections check the *product* (Quality Control).

    Common mistakes

    Confusing Audit (Process) with Inspection (Product).
    Question 104All questionsQuestion 106

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →