Hard1 markMultiple Choice
PMP · Question 106 · Task 4: Empower team members
A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is self-organizing. What should the PM do?
A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is self-organizing. What should the PM do?
Answer options:
A.
Assign tasks to team members.
B.
Provide the vision and boundaries (Goal/Constraints), then step back and let the team decide 'How' to do the work.
C.
Leave the team completely alone.
D.
Appoint a team lead to assign tasks.
How to approach this question
Self-organization needs Boundaries + Autonomy.
Full Answer
B.Provide the vision and boundaries (Goal/Constraints), then step back and let the team decide 'How' to do the work.✓ Correct
B
Task 2 (Lead) and Task 4 (Empower). Empowerment isn't chaos; it's autonomy within boundaries.
Common mistakes
Thinking self-organization means no management (C) or just delegation (A).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert