PMP · Question 09 · Task 13: Determine appropriate project methodology/methods and practices
A construction project for a new hospital has strict regulatory requirements, detailed architectural plans, and a fixed completion date. However, the medical equipment selection and interior design elements can evolve based on staff feedback during construction. Which project approach is MOST appropriate?
A construction project for a new hospital has strict regulatory requirements, detailed architectural plans, and a fixed completion date. However, the medical equipment selection and interior design elements can evolve based on staff feedback during construction. Which project approach is MOST appropriate?
Answer options:
Predictive approach because the regulatory requirements and fixed date require traditional planning
Agile approach because the evolving requirements for equipment and design need iterative delivery
Hybrid approach with predictive planning for construction and adaptive elements for equipment/design decisions
Iterative approach with multiple cycles allowing continuous refinement of all project aspects
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
Expert