Hard1 markMultiple Choice
PMP · Question 10 · Task 10: Manage project changes
A key stakeholder requests a significant feature addition during the execution phase of a predictive project. The change would add substantial business value but would impact the timeline by 6 weeks and increase the budget by 15%. What should the project manager do FIRST?
A key stakeholder requests a significant feature addition during the execution phase of a predictive project. The change would add substantial business value but would impact the timeline by 6 weeks and increase the budget by 15%. What should the project manager do FIRST?
Answer options:
A.
Implement the change immediately since it adds substantial business value
B.
Reject the change to protect the project baseline and maintain schedule commitments
C.
Assess the full impact on scope, schedule, cost, and quality, then submit to the change control board
D.
Negotiate with the stakeholder to defer the change to a future project phase
How to approach this question
In predictive projects, follow formal change control processes. Impact assessment must precede any decisions about accepting, rejecting, or modifying changes.
Full Answer
C.Assess the full impact on scope, schedule, cost, and quality, then submit to the change control board✓ Correct
Change control processes require thorough impact assessment before decision-making. This ensures informed decisions and maintains project governance.
Common mistakes
Making immediate decisions about changes without proper impact assessment, or bypassing established governance processes.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert