PMP · Question 100 · Task 17: Plan and manage project/phase closure or transitions
A project manager is preparing for project closure on a successful software development project. The deliverables have been accepted and the client is satisfied, but several team members have expressed interest in continuing to work together on future projects. What should the project manager do to maximize the value of this team experience?
Answer options:
Document the team composition and working agreements for future project reference
Recommend the team members for future projects based on their successful collaboration
Conduct a comprehensive lessons learned session focusing on what made the team successful and how to replicate it
Celebrate the team's success and maintain informal networks for future collaboration