    PracticePMI PMP®PMI PMP Practice Exam 3Question 13
    Hard1 markMultiple Choice
    Task 4: Engage stakeholdersstakeholder analysispower-interest gridstakeholder engagementinfluence management

    PMP · Question 13 · Task 4: Engage stakeholders

    A project manager is analyzing stakeholders for a new digital transformation initiative. The analysis reveals a department head who has high influence over project resources but low interest in the project outcomes, and a group of end users who have low influence but high interest in the project success. Which TWO stakeholder engagement strategies are MOST appropriate?

    Answer options:

    A.

    Keep the department head satisfied through regular updates and addressing their concerns

    B.

    Manage the department head closely with frequent detailed communications

    C.

    Monitor the end users with minimal communication

    D.

    Keep the end users informed about project progress and benefits

    E.

    Involve both groups equally in all project decisions

    F.

    Focus primarily on the department head since they have more influence

    How to approach this question

    Use the power-interest grid: high influence/low interest = keep satisfied; low influence/high interest = keep informed. Match strategies to stakeholder characteristics.

    Full Answer

    A,D
    Stakeholder engagement strategies should match their power-interest profile. High influence requires satisfaction, high interest requires information sharing.

    Common mistakes

    Treating all stakeholders the same way or focusing only on influence while ignoring interest levels. Each quadrant of the power-interest grid has different strategies.
    Question 12All questionsQuestion 14

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →