    PracticePMI PMP®PMI PMP Practice Exam 3Question 14
    Hard1 markMultiple Choice
    Task 3: Support team performanceservant leadershipteam member supportwork-life balanceindividual coaching

    PMP · Question 14 · Task 3: Support team performance

    A project manager discovers that a team member has been consistently working overtime to meet sprint commitments, but hasn't communicated this to anyone. The team member's work quality remains high, but the project manager is concerned about sustainability. What should the project manager do FIRST?

    Answer options:

    A.

    Have a private conversation with the team member to understand the situation and explore solutions

    B.

    Reduce the team member's workload in the next sprint to prevent burnout

    C.

    Bring up the issue in the next retrospective to get team input

    D.

    Document the overtime hours and report them to HR for policy compliance

    How to approach this question

    Servant leadership prioritizes understanding and supporting team members. Private conversations show care while gathering information to address root causes.

    Full Answer

    A.Have a private conversation with the team member to understand the situation and explore solutions✓ Correct
    A
    Servant leaders prioritize the well-being of their team members. Understanding the situation through private conversation enables appropriate support and solutions.

    Common mistakes

    Making assumptions about solutions without understanding the problem, or handling personal issues in public forums like retrospectives.
    Question 13All questionsQuestion 15

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →