Hard1 markShort Answer
Task 6: Plan and manage schedulePERTthree-point estimationschedule managementexpected duration

PMP · Question 25 · Task 6: Plan and manage schedule

A project has a three-point estimate for a critical path activity:<br/>- Optimistic (O): 8 days<br/>- Most Likely (M): 12 days<br/>- Pessimistic (P): 22 days<br/><br/>Using the PERT formula, calculate the expected duration for this activity. Round to one decimal place and enter numbers only (e.g., 12.5).

How to approach this question

Use the PERT formula: Expected Duration = (O + 4M + P) / 6. Substitute the values and calculate.

Full Answer

PERT expected duration = (O + 4M + P) / 6 = (8 + 4×12 + 22) / 6 = (8 + 48 + 22) / 6 = 78 / 6 = 13.0 days.

Common mistakes

Using simple average (O + M + P) / 3 instead of the weighted PERT formula, or calculation errors in the arithmetic.

Practice the full PMI PMP Practice Exam 3

100 questions · hints · full answers · grading

More questions from this exam