PMP · Question 26 · Task 11: Plan and manage procurement
A project manager is working on a complex integration project involving multiple vendors. One vendor consistently delivers components that meet specifications but require significant additional work to integrate with other systems. What should the project manager do to address this recurring issue?
A project manager is working on a complex integration project involving multiple vendors. One vendor consistently delivers components that meet specifications but require significant additional work to integrate with other systems. What should the project manager do to address this recurring issue?
Answer options:
Work with the vendor to improve their understanding of integration requirements and establish better acceptance criteria
Accept the additional integration work as part of the project scope since the components meet specifications
Replace the vendor with one that has better integration experience
Assign internal resources to handle all integration work for this vendor's components
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
Expert