    PracticePMI PMP®PMI PMP Practice Exam 3Question 37
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopetechnical debtclient requirementscollaborative problem solvingbusiness-technical alignment

    PMP · Question 37 · Task 8: Plan and manage scope

    A project manager is working on a software development project where the client has requested a feature that the technical team believes will create significant technical debt and maintenance challenges. The feature is not critical to core functionality but the client insists it's important for their business process. What should the project manager do?

    Answer options:

    A.

    Implement the feature as requested since the client is paying for the project

    B.

    Refuse to implement the feature due to technical debt concerns

    C.

    Facilitate a discussion between the client and technical team to explore alternatives that meet the business need with less technical risk

    D.

    Implement the feature but document the technical debt for future resolution

    How to approach this question

    When there's conflict between business needs and technical concerns, facilitate collaborative exploration of alternatives rather than choosing sides.

    Full Answer

    C.Facilitate a discussion between the client and technical team to explore alternatives that meet the business need with less technical risk✓ Correct
    C
    Facilitating collaboration between business and technical perspectives often reveals alternative solutions that meet business needs without creating technical problems.

    Common mistakes

    Either automatically accepting client requests or dismissing them based on technical concerns, instead of facilitating collaborative problem-solving.
    Question 36All questionsQuestion 38

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →