PMP · Question 36 · Task 2: Evaluate and deliver project benefits and value
A project manager discovers that the project's key performance indicators show the team is meeting all technical milestones, but stakeholder satisfaction surveys indicate declining confidence in the project's ability to deliver business value. What should the project manager do FIRST?
Answer options:
Engage with stakeholders to understand the disconnect between technical progress and perceived business value
Increase communication frequency to better inform stakeholders about technical progress
Review the project scope to ensure alignment with business objectives
Accelerate delivery to demonstrate business value sooner