PMP · Question 35 · Task 6: Build a team
A project manager is leading a team that includes both experienced and junior developers. During sprint planning, the experienced developers consistently estimate tasks much lower than the junior developers for similar work. This is causing confusion and making sprint planning difficult. What should the project manager do?
Answer options:
Use the estimates from experienced developers since they have more accurate historical data
Facilitate estimation discussions where team members explain their reasoning and reach consensus
Create separate estimation processes for experienced and junior developers
Average the estimates from experienced and junior developers for each task
100 questions · hints · full answers · grading