PMP · Question 34 · Task 11: Engage and support virtual teams
A project manager is working with a geographically distributed team across multiple time zones. Team members report feeling disconnected from each other and project decisions are taking longer than expected due to communication delays. What should the project manager do to improve team cohesion and decision-making efficiency?
A project manager is working with a geographically distributed team across multiple time zones. Team members report feeling disconnected from each other and project decisions are taking longer than expected due to communication delays. What should the project manager do to improve team cohesion and decision-making efficiency?
Answer options:
Require all team members to work during overlapping hours to improve real-time communication
Implement more frequent video conferences to increase face-to-face interaction
Establish multiple communication channels and decision-making protocols that accommodate asynchronous work
Rotate meeting times so that different team members take turns with inconvenient schedules
How to approach this question
Full Answer
Common mistakes