PMP · Question 33 · Task 17: Plan and manage project/phase closure or transitions
A project manager is planning the closure of a successful project. The project deliverables have been accepted, but there are several lessons learned that could benefit future projects. The team is eager to move on to new assignments. Which TWO actions should the project manager prioritize during project closure?
A project manager is planning the closure of a successful project. The project deliverables have been accepted, but there are several lessons learned that could benefit future projects. The team is eager to move on to new assignments. Which TWO actions should the project manager prioritize during project closure?
Answer options:
Conduct an extensive post-project review with all stakeholders
Capture and document key lessons learned while team knowledge is still fresh
Celebrate project success with the team before they disperse
Ensure proper knowledge transfer to operations or maintenance teams
Complete all administrative closure activities like contract closeouts
Archive all project documentation for future reference
How to approach this question