PMP · Question 32 · Task 15: Manage project issues
A project manager discovers that a critical project issue has been escalated to senior management without their knowledge. The issue was escalated by a team member who felt their concerns weren't being addressed through normal channels. What should the project manager do FIRST?
Answer options:
Meet with the team member to understand their concerns and why they felt escalation was necessary
Address the issue with senior management to provide context and project perspective
Remind the team about proper escalation procedures and communication channels
Document the incident and discuss it with the team member's functional manager
100 questions · hints · full answers · grading