PMP · Question 39 · Task 10: Manage project changes
A project manager is working on a predictive project where a major scope change has been approved by the change control board. The change will add 4 weeks to the schedule and $50,000 to the budget. However, implementing the change will require rework of already completed deliverables. What should the project manager do FIRST?
Answer options:
Begin implementing the change immediately since it has been approved
Develop a detailed implementation plan that minimizes rework and optimizes the integration of changes
Communicate the change to all stakeholders and update project documentation
Assess whether the approved change is still the best option given the rework requirements