Hard1 markShort Answer
Task 6: Plan and manage schedulecritical path methodnetwork diagramproject durationschedule management

PMP · Question 43 · Task 6: Plan and manage schedule

A project has the following network diagram with activity durations:<br/>Activity A: 5 days (no predecessors)<br/>Activity B: 8 days (predecessor: A)<br/>Activity C: 6 days (predecessor: A)<br/>Activity D: 4 days (predecessors: B, C)<br/>Activity E: 7 days (predecessor: D)<br/><br/>What is the total project duration in days? Enter numbers only.

How to approach this question

Identify the critical path by finding the longest path through the network. Calculate the total duration along this path.

Full Answer

24
Critical path analysis: A→B→D→E = 5+8+4+7 = 24 days. A→C→D→E = 5+6+4+7 = 22 days. The critical path is 24 days.

Common mistakes

Adding all activity durations instead of finding the critical path, or incorrectly calculating the longest path through the network.

Practice the full PMI PMP Practice Exam 3

100 questions · hints · full answers · grading

More questions from this exam