PMP · Question 43 · Task 6: Plan and manage schedule
A project has the following network diagram with activity durations:<br/>Activity A: 5 days (no predecessors)<br/>Activity B: 8 days (predecessor: A)<br/>Activity C: 6 days (predecessor: A)<br/>Activity D: 4 days (predecessors: B, C)<br/>Activity E: 7 days (predecessor: D)<br/><br/>What is the total project duration in days? Enter numbers only.
100 questions · hints · full answers · grading