For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 3Question 43
    Hard1 markShort Answer
    Task 6: Plan and manage schedulecritical path methodnetwork diagramproject durationschedule management

    PMP · Question 43 · Task 6: Plan and manage schedule

    A project has the following network diagram with activity durations:<br/>Activity A: 5 days (no predecessors)<br/>Activity B: 8 days (predecessor: A)<br/>Activity C: 6 days (predecessor: A)<br/>Activity D: 4 days (predecessors: B, C)<br/>Activity E: 7 days (predecessor: D)<br/><br/>What is the total project duration in days? Enter numbers only.

    How to approach this question

    Identify the critical path by finding the longest path through the network. Calculate the total duration along this path.

    Full Answer

    Critical path analysis: A→B→D→E = 5+8+4+7 = 24 days. A→C→D→E = 5+6+4+7 = 22 days. The critical path is 24 days.

    Common mistakes

    Adding all activity durations instead of finding the critical path, or incorrectly calculating the longest path through the network.
    Question 42All questionsQuestion 44

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →