PMP · Question 45 · Task 8: Plan and manage scope
A project manager discovers that a team member has been working on tasks that are not in the current sprint backlog. When questioned, the team member explains they thought these tasks were important for the overall project success. What should the project manager do FIRST?
Answer options:
Understand the team member's reasoning and assess whether the work adds value to project objectives
Redirect the team member to focus only on sprint backlog items
Discuss the importance of following sprint commitments with the entire team
Add the completed work to the sprint backlog retroactively