Hard1 markMultiple Choice
PMP · Question 45 · Task 8: Plan and manage scope
A project manager discovers that a team member has been working on tasks that are not in the current sprint backlog. When questioned, the team member explains they thought these tasks were important for the overall project success. What should the project manager do FIRST?
A project manager discovers that a team member has been working on tasks that are not in the current sprint backlog. When questioned, the team member explains they thought these tasks were important for the overall project success. What should the project manager do FIRST?
Answer options:
A.
Understand the team member's reasoning and assess whether the work adds value to project objectives
B.
Redirect the team member to focus only on sprint backlog items
C.
Discuss the importance of following sprint commitments with the entire team
D.
Add the completed work to the sprint backlog retroactively
How to approach this question
When team members take initiative outside planned work, understand their reasoning and assess value before taking corrective action.
Full Answer
A.Understand the team member's reasoning and assess whether the work adds value to project objectives✓ Correct
A
Understanding the team member's reasoning helps determine if valuable work was done and informs how to handle similar situations in the future.
Common mistakes
Immediately correcting the process violation without understanding the potential value of the work or the team member's reasoning.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert