Hard1 markMultiple Choice
Task 10: Manage project changesurgent changessecurity requirementschange managementimpact assessment

PMP · Question 47 · Task 10: Manage project changes

A project manager is working on a software development project where the client has requested additional security features after a recent industry security breach. The features were not in the original scope but are now considered essential. The development team estimates the work will take 3 weeks and require specialized security expertise. What should the project manager do FIRST?

Answer options:

A.

Implement the security features immediately since they are essential for project success

B.

Negotiate with the client to defer security features to a future release

C.

Assess the full impact of the security requirements on scope, schedule, cost, and resources, then follow change management processes

D.

Begin recruiting specialized security expertise while continuing with current development work

How to approach this question

Even urgent or essential changes require proper impact assessment and change management processes to ensure successful implementation.

Full Answer

C.Assess the full impact of the security requirements on scope, schedule, cost, and resources, then follow change management processes✓ Correct
C
Urgent changes still require impact assessment and proper change management to ensure they're implemented successfully without unintended consequences.

Common mistakes

Bypassing change management processes for urgent changes, which can lead to implementation problems and uncontrolled scope creep.