PMP · Question 50 · Task 6: Build a team
A project manager is leading a team that includes both permanent employees and contractors. The permanent employees have access to internal systems and information that contractors do not, creating information asymmetries that affect collaboration. What should the project manager do to address this challenge?
A project manager is leading a team that includes both permanent employees and contractors. The permanent employees have access to internal systems and information that contractors do not, creating information asymmetries that affect collaboration. What should the project manager do to address this challenge?
Answer options:
Request that contractors be given the same system access as permanent employees
Assign permanent employees to share relevant information with contractors as needed
Establish information sharing protocols and collaboration processes that work within security constraints
Organize the team so that contractors and permanent employees work on separate tasks
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
Expert