For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 3Question 56
    Hard1 markShort Answer
    Task 6: Plan and manage scheduleearned value managementSPI calculationschedule performanceproject control

    PMP · Question 56 · Task 6: Plan and manage schedule

    A project has the following earned value data at the end of month 6:<br/>- Planned Value (PV): $180,000<br/>- Earned Value (EV): $150,000<br/>- Actual Cost (AC): $165,000<br/><br/>Calculate the Schedule Performance Index (SPI). Round to two decimal places and enter numbers only (e.g., 0.85).

    How to approach this question

    Use the SPI formula: SPI = EV / PV. Substitute the values and calculate to two decimal places.

    Full Answer

    SPI = EV / PV = $150,000 / $180,000 = 0.83. This indicates the project is earning value at 83% of the planned rate, suggesting schedule delays.

    Common mistakes

    Confusing SPI with CPI (using AC instead of PV), or calculation errors in the division.
    Question 55All questionsQuestion 57

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →