    PracticePMI PMP®PMI PMP Practice Exam 3Question 58
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceconfidentiality breachpolicy violationteam member coachinginformation security

    PMP · Question 58 · Task 1: Plan and manage project compliance

    A project manager discovers that a team member has been sharing confidential project information with colleagues outside the project team. The information sharing appears to be inadvertent rather than malicious, but it violates project confidentiality agreements. What should the project manager do FIRST?

    Answer options:

    A.

    Have a private conversation with the team member to understand the situation and reinforce confidentiality requirements

    B.

    Report the confidentiality breach to senior management immediately

    C.

    Remind the entire team about confidentiality requirements without singling out the individual

    D.

    Document the incident and monitor the team member's future behavior

    How to approach this question

    For inadvertent policy violations, direct conversation to understand the situation and reinforce requirements is typically the appropriate first step.

    Full Answer

    A.Have a private conversation with the team member to understand the situation and reinforce confidentiality requirements✓ Correct
    Direct conversation allows the project manager to understand whether the breach was truly inadvertent and ensures the team member understands confidentiality requirements.

    Common mistakes

    Either immediately escalating inadvertent violations or avoiding direct conversation, both of which may not effectively address the issue.
    Question 57All questionsQuestion 59

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →