    PracticePMI PMP®PMI PMP Practice Exam 3Question 63
    Hard1 markMultiple Choice
    Task 10: Manage project changeschanging requirementsstakeholder-team alignmentchange managementmarket adaptation

    PMP · Question 63 · Task 10: Manage project changes

    A project manager is working on a project where stakeholder requirements keep evolving due to changing market conditions. The development team is frustrated with the constant changes and wants more stability. The business stakeholders insist the changes are necessary for project success. What should the project manager do?

    Answer options:

    A.

    Implement a change freeze to provide stability for the development team

    B.

    Facilitate discussions between stakeholders and the development team to improve understanding and find ways to manage change more effectively

    C.

    Switch to a more agile methodology that better accommodates changing requirements

    D.

    Create a buffer in the schedule to accommodate ongoing requirement changes

    How to approach this question

    When stakeholders and teams have conflicting needs regarding change, facilitate understanding and collaborative development of better change management approaches.

    Full Answer

    B.Facilitate discussions between stakeholders and the development team to improve understanding and find ways to manage change more effectively✓ Correct
    Facilitating understanding between stakeholders and teams helps develop change management approaches that balance business needs with team effectiveness.

    Common mistakes

    Either stopping changes (ignoring business needs) or allowing unlimited changes (ignoring team needs) instead of facilitating better change management.
    Question 62All questionsQuestion 64

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →