Hard1 markMultiple Choice
Task 9: Integrate project planning activitiestechnical incompatibilityintegration issuesimpact assessmentresolution options
PMP · Question 62 · Task 9: Integrate project planning activities
A project manager discovers that two different teams working on related project components have developed incompatible technical approaches. The incompatibility wasn't discovered until integration testing began. What should the project manager do FIRST?
A project manager discovers that two different teams working on related project components have developed incompatible technical approaches. The incompatibility wasn't discovered until integration testing began. What should the project manager do FIRST?
Answer options:
A.
Determine which team's approach is technically superior and require the other team to adapt
B.
Require both teams to start over with a coordinated approach
C.
Assess the impact of the incompatibility and evaluate options for resolution, including technical and schedule implications
D.
Escalate the technical incompatibility to senior management for resolution
How to approach this question
When facing technical incompatibilities, comprehensive impact assessment should precede decisions about resolution approaches.
Full Answer
C.Assess the impact of the incompatibility and evaluate options for resolution, including technical and schedule implications✓ Correct
C
Technical incompatibilities require comprehensive assessment of impact and resolution options to determine the most effective approach considering all project constraints.
Common mistakes
Making immediate decisions about which approach to use without assessing the full impact and available resolution options.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert