Hard1 markMultiple Choice
PMP · Question 79 · Task 1: Manage conflict
A project manager is leading a team where a senior team member frequently interrupts others during meetings and dominates discussions. This is preventing other team members from contributing and affecting team dynamics. What should the project manager do?
A project manager is leading a team where a senior team member frequently interrupts others during meetings and dominates discussions. This is preventing other team members from contributing and affecting team dynamics. What should the project manager do?
Answer options:
A.
Speak with the senior team member privately after the next meeting where this behavior occurs
B.
Have a private conversation with the senior team member about the impact of their behavior on team participation
C.
Implement structured meeting formats that limit individual speaking time
D.
Address the behavior publicly in the next team meeting to set expectations
How to approach this question
When team members exhibit disruptive behavior, address it directly and privately, focusing on impact rather than personal criticism.
Full Answer
B.Have a private conversation with the senior team member about the impact of their behavior on team participation✓ Correct
B
Disruptive behavior should be addressed promptly and privately, focusing on the impact on team dynamics rather than personal criticism to encourage behavior change.
Common mistakes
Either waiting for the behavior to continue or addressing it publicly, both of which can worsen team dynamics rather than improving them.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert