    PracticePMI PMP®PMI PMP Practice Exam 3Question 87
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksexperimental technologycompetitive advantagerisk-benefit analysisinformed decision making

    PMP · Question 87 · Task 3: Assess and manage risks

    A project manager is working on a project where the client has requested a feature that would significantly differentiate their product in the market. However, implementing this feature would require the team to work with experimental technology that has limited documentation and support. What should the project manager do?

    Answer options:

    A.

    Recommend against using experimental technology due to the associated risks

    B.

    Implement the feature using the experimental technology since it provides competitive advantage

    C.

    Present a comprehensive analysis of the competitive benefits, technical risks, support limitations, and mitigation strategies

    D.

    Propose a phased approach starting with a proof of concept to evaluate the experimental technology

    How to approach this question

    When clients want features using experimental technology, provide comprehensive risk-benefit analysis to enable informed business decisions rather than making technical recommendations.

    Full Answer

    C.Present a comprehensive analysis of the competitive benefits, technical risks, support limitations, and mitigation strategies✓ Correct
    C
    Decisions about experimental technology require balancing competitive benefits against technical risks. Clients need complete information to make informed business decisions.

    Common mistakes

    Making technical recommendations based on risk aversion or competitive potential instead of providing comprehensive analysis for informed business decision-making.
    Question 86All questionsQuestion 88

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard