    PracticePMI PMP®PMI PMP Practice Exam 3Question 94
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopearchitectural changestechnical debtbusiness value analysisinformed decision making

    PMP · Question 94 · Task 8: Plan and manage scope

    A project manager is working on a project where the client has requested a feature that would require significant changes to the system architecture. The development team estimates this would take 6 weeks and create technical debt that could affect future maintenance. The feature would provide moderate business value. What should the project manager do?

    Answer options:

    A.

    Recommend against the feature due to the architectural impact and technical debt concerns

    B.

    Present the client with a comprehensive analysis of business value, architectural impact, technical debt implications, and alternative approaches

    C.

    Implement the feature as requested since the client understands their business needs best

    D.

    Propose alternative implementations that provide similar business value with less architectural impact

    How to approach this question

    When features require significant architectural changes, provide comprehensive analysis of business value, technical impact, and alternatives to enable informed client decisions.

    Full Answer

    B.Present the client with a comprehensive analysis of business value, architectural impact, technical debt implications, and alternative approaches✓ Correct
    Architectural decisions involve complex trade-offs between business value and technical costs. Clients need complete information about implications and alternatives to make informed decisions.

    Common mistakes

    Either making technical recommendations or implementing without ensuring the client understands the full architectural implications and long-term costs.
    Question 93All questionsQuestion 95

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard