Hard1 markMultiple Choice
Task 2: Manage communicationscommunication protocolsgovernance bypassroot cause analysiscommunication plan gaps
PMP · Question 97 · Task 2: Manage communications
A project manager discovers that a team member has been sharing project status information with stakeholders outside the approved communication plan. The information shared is accurate but bypasses the established governance structure. What should the project manager do FIRST?
A project manager discovers that a team member has been sharing project status information with stakeholders outside the approved communication plan. The information shared is accurate but bypasses the established governance structure. What should the project manager do FIRST?
Answer options:
A.
Meet with the team member to understand why they felt the need to communicate outside the established channels
B.
Remind the team member about the importance of following the communication plan
C.
Report the communication plan violation to the team member's manager
D.
Update the communication plan to include the stakeholders who received the information
How to approach this question
When team members bypass communication protocols, understand the root cause first, as it may reveal gaps in the communication plan or unmet stakeholder needs.
Full Answer
A.Meet with the team member to understand why they felt the need to communicate outside the established channels✓ Correct
Bypassing communication protocols may indicate gaps in the communication plan or unmet stakeholder needs. Understanding the root cause enables appropriate response.
Common mistakes
Treating this as a compliance issue without understanding whether there were legitimate reasons for the communication that indicate communication plan gaps.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert