    PracticePMI PMP®PMI PMP Practice Exam 4Question 48
    Hard1 markMultiple Choice
    Task 12: Define team ground rulesteam ground rulesteam chartercross-functional teamsworking agreements

    PMP · Question 48 · Task 12: Define team ground rules

    A new cross-functional team is forming for a critical customer-facing project. The team includes members from development, QA, UX design, and customer support, each with different working styles and communication preferences. Some team members prefer detailed planning while others favor adaptive approaches. The project requires close collaboration and rapid decision-making. What should the project manager do FIRST?

    Answer options:

    A.

    Facilitate a team charter session where members collaboratively establish working agreements, communication norms, and decision-making processes

    B.

    Implement the organization's standard cross-functional team practices

    C.

    Assign team roles and responsibilities based on functional expertise

    D.

    Start with basic project activities and let team norms develop naturally over time

    How to approach this question

    Look for collaborative approaches that involve all team members in establishing ground rules that address their specific composition and needs.

    Full Answer

    A.Facilitate a team charter session where members collaboratively establish working agreements, communication norms, and decision-making processes✓ Correct
    A
    Effective team ground rules require collaborative development that addresses the specific mix of working styles, communication preferences, and decision-making needs within the team.

    Common mistakes

    Students often choose standard practices or role-based approaches rather than recognizing the need for collaborative ground rule development.
    Question 47All questionsQuestion 49

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard