    PracticePMI PMP®PMI PMP Practice Exam 4Question 66
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transfer for project continuityknowledge transferoperations transitionoperational readinesscapability building

    PMP · Question 66 · Task 16: Ensure knowledge transfer for project continuity

    A project manager is preparing for the transition of a complex e-commerce platform from the development team to the operations and support teams. The operations team has limited experience with the new technology stack and microservices architecture. The development team has focused on feature delivery and has not created comprehensive operational documentation or troubleshooting guides. What should the project manager do FIRST?

    Answer options:

    A.

    Schedule comprehensive training sessions for the operations team on the new technology stack and architecture

    B.

    Extend the development team's involvement to provide ongoing operational support during the transition period

    C.

    Conduct a comprehensive knowledge transfer assessment to identify operational knowledge gaps and develop a structured transfer plan

    D.

    Create detailed operational documentation and troubleshooting procedures for all system components

    How to approach this question

    Look for systematic approaches that assess operational knowledge gaps and develop comprehensive transfer plans based on operations team needs.

    Full Answer

    C.Conduct a comprehensive knowledge transfer assessment to identify operational knowledge gaps and develop a structured transfer plan✓ Correct
    C
    Effective knowledge transfer for operations requires systematic assessment of existing operational knowledge, identification of gaps, and understanding of operations team needs to develop comprehensive transfer plans.

    Common mistakes

    Students often choose training or documentation approaches rather than recognizing the need to assess operational knowledge gaps and transfer requirements first.
    Question 65All questionsQuestion 67

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →