PMP · Question 08 · Task 10: Manage project changes
A key stakeholder requests a significant feature addition during the execution phase of a predictive project. The change would add substantial business value but would impact the timeline by 6 weeks and increase the budget by 15%. The stakeholder has significant organizational influence. What should the project manager do FIRST?
Answer options:
Implement the change immediately to maintain the relationship with the influential stakeholder
Reject the change request to protect the project baseline and original commitments
Assess the impact on scope, schedule, and cost, then submit the request to the change control board
Negotiate with the stakeholder to defer the change to a future project phase or release
94 questions · hints · full answers · grading