PMI PMP Practice Exam 5
94 free questions · No sign-up required to browse
This practice exam is designed to help you prepare for the PMI Project Management Professional (PMP) certification. It includes 94 challenging questions that cover a wide range of project management topics, including project integration, scope, schedule, cost, quality, resource management, communication, risk management, procurement, stakeholder management, and professional responsibility. Each question is crafted to test your knowledge and application of project management principles in real-world scenarios.
Topics covered
Browse all topics →Sample questions
During a sprint retrospective in an agile project, two senior developers engage in a heated argument about coding standards. The disagreement escalates when one developer questions the other's technical competence in front of the entire team. Team morale visibly drops, and other members become uncomfortable. What should the project manager do FIRST?
A project manager is leading a hybrid software development project where the client has clearly defined requirements that are unlikely to change, but wants to see incremental delivery every six weeks to demonstrate progress to their board of directors. The development team is experienced with both waterfall and agile methodologies. Which development approach is MOST appropriate for this scenario?
A project manager notices that a high-performing team member has become withdrawn over the past two weeks, is frequently late to daily stand-ups, and the quality of their deliverables has declined. Other team members have started expressing concerns about delays caused by this person's work. Which TWO emotional intelligence competencies should the project manager primarily apply in this situation?
During iteration planning for a hybrid software project, the team identifies a new technical risk: the third-party API they planned to integrate may not support the required data volume for the upcoming release. This could impact the sprint goal and the planned release date. What should the project manager do FIRST?
A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>The project manager needs to calculate the Estimate at Completion (EAC) assuming current performance will continue for the remainder of the project. What is the EAC? (Round to the nearest dollar, enter numbers only)
Ready to Practice the full exam?
All 94 questions with worked answers, mark schemes, and AI tutoring.
Expert