    PracticePMI PMP®PMI PMP Practice Exam 5Question 93
    Hard1 markMultiple Choice
    Task 4: Support organizational changeorganizational changedigital transformationchange resistancecultural assessment

    PMP · Question 93 · Task 4: Support organizational change

    A project manager is leading a digital transformation initiative that will significantly change how employees perform their daily work. Early feedback indicates strong resistance from department managers who are concerned about losing control over their processes and potential staff reductions. The resistance is beginning to affect project progress and stakeholder support. What should the project manager do FIRST?

    Answer options:

    A.

    Escalate the resistance issues to senior leadership for resolution

    B.

    Assess the organizational culture and understand the specific concerns driving the resistance

    C.

    Implement additional change management training and communication programs

    D.

    Modify the project approach to give department managers more control over the transformation process

    How to approach this question

    When facing organizational resistance to digital transformation, assess culture and understand specific concerns before implementing change management strategies or escalating issues.

    Full Answer

    B.Assess the organizational culture and understand the specific concerns driving the resistance✓ Correct
    Organizational change management requires understanding the cultural context and specific concerns driving resistance to develop targeted strategies that address root causes rather than symptoms.

    Common mistakes

    Students often choose escalation (A) or immediate solutions like training (C), missing the need to first understand organizational culture and specific resistance concerns.
    Question 92All questionsQuestion 94

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard