Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned value managementCPI calculationcost performanceproject metrics
PMP · Question 88 · Task 5: Plan and manage budget and resources
A project has the following earned value metrics at the end of Month 10:<br/>- Budget at Completion (BAC): $1,200,000<br/>- Planned Value (PV): $800,000<br/>- Earned Value (EV): $700,000<br/>- Actual Cost (AC): $750,000<br/><br/>What is the Cost Performance Index (CPI)? (Round to two decimal places, enter numbers only)
A project has the following earned value metrics at the end of Month 10:<br/>- Budget at Completion (BAC): $1,200,000<br/>- Planned Value (PV): $800,000<br/>- Earned Value (EV): $700,000<br/>- Actual Cost (AC): $750,000<br/><br/>What is the Cost Performance Index (CPI)? (Round to two decimal places, enter numbers only)
How to approach this question
Calculate CPI using the formula: CPI = EV / AC. Round to two decimal places and enter numbers only.
Full Answer
CPI = EV / AC = 700,000 / 750,000 = 0.93. A CPI less than 1.0 indicates the project is over budget.
Common mistakes
Students often confuse CPI with SPI (EV/PV) or calculate incorrectly by using PV instead of AC in the denominator.
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard