PMP · Question 88 · Task 5: Plan and manage budget and resources
A project has the following earned value metrics at the end of Month 10:<br/>- Budget at Completion (BAC): $1,200,000<br/>- Planned Value (PV): $800,000<br/>- Earned Value (EV): $700,000<br/>- Actual Cost (AC): $750,000<br/><br/>What is the Cost Performance Index (CPI)? (Round to two decimal places, enter numbers only)