For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®TopicsProcessTask 5: Plan and manage budget and resources
    Process

    Task 5: Plan and manage budget and resources

    15 questions across 5 exams

    Other subtopics in Process
    Task 1: Execute project with the urgency required to deliver business value13qTask 10: Manage project changes17qTask 11: Plan and manage procurement14qTask 12: Manage project artifacts11qTask 13: Determine appropriate project methodology/methods and practices18qTask 14: Establish project governance structure8qTask 15: Manage project issues10qTask 16: Ensure knowledge transfer for project continuity11qTask 17: Plan and manage project/phase closure or transitions9qTask 2: Manage communications14qTask 3: Assess and manage risks16qTask 4: Engage stakeholders18qTask 6: Plan and manage schedule19qTask 7: Plan and manage quality of products/deliverables17qTask 8: Plan and manage scope17qTask 9: Integrate project planning activities11q

    Covered in these exams

    PMI PMP Practice Exam 2PMI PMP Practice Exam 3PMI PMP Practice Exam 4PMI PMP Practice Exam 5PMI PMP Practice Exam 6

    All questions (15)

    Q05Hard1 mark·PMI PMP Practice Exam 2

    A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>The project manager needs to calculate the Estimate at Completion (EAC) assuming current cost performance will continue for the remainder of the project. What is the EAC? (Round to the nearest dollar, enter numbers only)

    Worked answer available with free account
    View question →
    Q91Hard1 mark·PMI PMP Practice Exam 2

    A project has the following earned value data:<br/><br/>- Budget at Completion (BAC): $800,000<br/>- Earned Value (EV): $480,000<br/>- Actual Cost (AC): $520,000<br/><br/>Assuming current cost performance continues, what is the To Complete Performance Index (TCPI) based on BAC? (Round to two decimal places, enter numbers only)

    Worked answer available with free account
    View question →
    Q98Hard1 mark·PMI PMP Practice Exam 2

    A project manager is leading a project that requires specialized expertise that is not available within the current team. The organization has budget constraints that make hiring additional full-time staff difficult. The project timeline is tight, and the specialized work is needed soon. What should the project manager do FIRST?

    Worked answer available with free account
    View question →
    Q05Hard1 mark·PMI PMP Practice Exam 3

    A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completion (BAC): $750,000<br/>- Planned Value (PV): $450,000<br/>- Earned Value (EV): $375,000<br/>- Actual Cost (AC): $420,000<br/><br/>Calculate the Estimate at Completion (EAC) assuming current cost performance will continue for the remainder of the project. Round to the nearest dollar and enter numbers only.

    Worked answer available with free account
    View question →
    Q69Hard1 mark·PMI PMP Practice Exam 3

    A project has the following earned value data:<br/>- Budget at Completion (BAC): $500,000<br/>- Earned Value (EV): $200,000<br/>- Actual Cost (AC): $250,000<br/>- Current CPI: 0.80<br/><br/>Calculate the To-Complete Performance Index (TCPI) based on the Budget at Completion. Round to two decimal places and enter numbers only (e.g., 1.25).

    Worked answer available with free account
    View question →
    Q19Hard1 mark·PMI PMP Practice Exam 4

    A project has the following earned value data at the end of month 8:<br/>- Budget at Completion (BAC): $800,000<br/>- Planned Value (PV): $480,000<br/>- Earned Value (EV): $400,000<br/>- Actual Cost (AC): $450,000<br/><br/>Calculate the Cost Performance Index (CPI). Round to two decimal places and enter numbers only (e.g., 0.89).

    Worked answer available with free account
    View question →
    Q55Hard1 mark·PMI PMP Practice Exam 4

    A project has the following earned value data at month 12:<br/>- Budget at Completion (BAC): $2,000,000<br/>- Earned Value (EV): $1,400,000<br/>- Actual Cost (AC): $1,600,000<br/>- Planned Value (PV): $1,500,000<br/><br/>Calculate the Estimate at Completion (EAC) assuming current performance trends will continue. Round to the nearest dollar and enter numbers only (e.g., 2285714).

    Worked answer available with free account
    View question →
    Q79Hard1 mark·PMI PMP Practice Exam 4

    A project has the following earned value data at the end of month 6:<br/>- Budget at Completion (BAC): $900,000<br/>- Earned Value (EV): $450,000<br/>- Actual Cost (AC): $500,000<br/>- Planned Value (PV): $480,000<br/><br/>Calculate the To Complete Performance Index (TCPI) based on the Budget at Completion. Round to two decimal places and enter numbers only (e.g., 1.11).

    Worked answer available with free account
    View question →
    Q05Hard1 mark·PMI PMP Practice Exam 5

    A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>The project manager needs to calculate the Estimate at Completion (EAC) assuming current performance will continue for the remainder of the project. What is the EAC? (Round to the nearest dollar, enter numbers only)

    Worked answer available with free account
    View question →
    Q21Hard1 mark·PMI PMP Practice Exam 5

    A project manager is reviewing the budget performance and notices that the project is currently over budget due to higher than expected resource costs. The sponsor is concerned about cost overruns and wants to understand the future budget implications. The project is 60% complete with a CPI of 0.85. What should the project manager do FIRST?

    Worked answer available with free account
    View question →
    Q56Hard1 mark·PMI PMP Practice Exam 5

    A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completion (BAC): $800,000<br/>- Planned Value (PV): $500,000<br/>- Earned Value (EV): $400,000<br/>- Actual Cost (AC): $450,000<br/><br/>What is the Schedule Performance Index (SPI)? (Round to two decimal places, enter numbers only)

    Worked answer available with free account
    View question →
    Q88Hard1 mark·PMI PMP Practice Exam 5

    A project has the following earned value metrics at the end of Month 10:<br/>- Budget at Completion (BAC): $1,200,000<br/>- Planned Value (PV): $800,000<br/>- Earned Value (EV): $700,000<br/>- Actual Cost (AC): $750,000<br/><br/>What is the Cost Performance Index (CPI)? (Round to two decimal places, enter numbers only)

    Worked answer available with free account
    View question →
    Q19Hard1 mark·PMI PMP Practice Exam 6

    A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>Calculate the Estimate at Completion (EAC) assuming current performance will continue for the remainder of the project. Round to the nearest dollar and enter numbers only.

    Worked answer available with free account
    View question →
    Q54Hard1 mark·PMI PMP Practice Exam 6

    A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completion (BAC): $800,000<br/>- Planned Value (PV): $480,000<br/>- Earned Value (EV): $400,000<br/>- Actual Cost (AC): $450,000<br/><br/>Calculate the Schedule Performance Index (SPI). Round to two decimal places and enter numbers only.

    Worked answer available with free account
    View question →
    Q89Hard1 mark·PMI PMP Practice Exam 6

    A project has the following earned value metrics at the end of Month 10:<br/>- Budget at Completion (BAC): $1,200,000<br/>- Planned Value (PV): $720,000<br/>- Earned Value (EV): $600,000<br/>- Actual Cost (AC): $680,000<br/><br/>Calculate the Cost Performance Index (CPI). Round to two decimal places and enter numbers only.

    Worked answer available with free account
    View question →

    Practice these questions with detailed guidance

    Full answers, grading, and explanations on why each answer is correct.

    Sign up freeBrowse exams