PMI PMP®

PMI PMP Practice Exam 2

100 free questions · No sign-up required to browse

A comprehensive practice exam based on the current PMP Examination Content Outline (ECO) 2021. This exam covers all three domains: People (42%), Process (50%), and Business Environment (8%) with questions requiring deep understanding of project management principles, servant leadership, and modern methodologies including predictive, agile, and hybrid approaches. Questions are designed to test application, analysis, and synthesis of PM concepts in complex, real-world scenarios.

100
Questions
Hard
Difficulty
90%
Pass mark

Topics covered

Browse all topics →

Sample questions

Q01Hard1 mark

During a sprint planning meeting in a hybrid project, two senior developers disagree about the technical approach for implementing a critical security feature. The disagreement is becoming heated, with each developer questioning the other's expertise. The team's morale is visibly affected, and other team members are becoming uncomfortable. What should the project manager do FIRST?

View question with guidance →
Q02Hard1 mark

A project manager is assigned to lead a new software development project for a financial services company. The client has clearly defined requirements that are unlikely to change due to regulatory constraints, but wants incremental delivery every six weeks to show progress to stakeholders and gather early feedback on user interface elements. The development team is experienced with both predictive and agile methodologies. Which development approach is MOST appropriate?

View question with guidance →
Q03Hard1 mark

During iteration planning for a hybrid software project, the team identifies a new technical risk: the third-party API they planned to integrate may not support the required data volume for peak usage periods. This could impact the current sprint goal and the upcoming release to production. The team estimates this affects 40% of the planned sprint work. Which TWO actions should the project manager take FIRST to address this risk?

View question with guidance →
Q04Hard1 mark

A construction company is building a hospital with strict regulatory requirements, detailed architectural plans, and a fixed completion date for the opening. However, the medical equipment selection and interior design can evolve based on staff feedback during construction, and the hospital administration wants to see progress on these elements every month. Which project approach would be MOST appropriate for this scenario?

View question with guidance →
Q05Hard1 mark

A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>The project manager needs to calculate the Estimate at Completion (EAC) assuming current cost performance will continue for the remainder of the project. What is the EAC? (Round to the nearest dollar, enter numbers only)

View question with guidance →

Ready to Practice the full exam?

All 100 questions with worked answers, mark schemes, and AI tutoring.

All questions (100)

Free to browse · no sign-up required
Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the technical approach for...HardQ02A project manager is assigned to lead a new software development project for a financial services company. The client...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk: the third-party AP...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed architectural plans, and ...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br...HardQ06A project manager notices that a highly skilled team member has become withdrawn over the past two weeks, is missing ...HardQ07A software project team has been tracking defects found during testing sprints. The data shows:<br/><br/>| Sprint | D...HardQ08A pharmaceutical company project must comply with FDA regulations for clinical trial data management. During a routin...HardQ09An agile development team reports during the daily stand-up that they cannot proceed with testing the core authentica...HardQ10A key stakeholder requests a significant feature addition during the execution phase of a predictive project. The cha...HardQ11A project team is distributed across three time zones with members in New York, London, and Mumbai. During virtual me...HardQ12During a project retrospective, the team identifies that they consistently underestimate the effort required for inte...HardQ13A project manager is leading a digital transformation initiative that will significantly change how employees work. T...HardQ14A project team member approaches the project manager privately and reports that another team member has been claiming...HardQ15A project is implementing a new customer relationship management (CRM) system. The business stakeholders want to see ...HardQ16During a project status meeting, a functional manager questions the project manager's decision to use an agile approa...HardQ17A team member consistently delivers high-quality work but struggles with time management and frequently misses deadli...HardQ18A project manager discovers that a critical vendor has been acquired by a competitor, and the new ownership is discon...HardQ19A project team is working on developing a mobile application using Scrum methodology. During the sprint review, stake...HardQ20A project manager is leading a team that includes both experienced senior developers and recent graduates. The senior...HardQ21A project manager is reviewing the project's risk register and notices that a risk identified three months ago as 'lo...HardQ22A project team has established ground rules including 'all team members will be respectful in communications' and 'de...HardQ23A project manager receives conflicting requirements from two key stakeholders. The marketing director wants the produ...HardQ24During project execution, the project manager discovers that a team member has been working on tasks that are not in ...HardQ25A project manager is leading a cross-functional team where members report to different functional managers. One team ...HardQ26A project team is using Kanban to manage their workflow. The team notices that work items are spending too much time ...HardQ27A project manager is working with a new team member who has strong technical skills but lacks experience with the org...HardQ28A project is nearing completion, and the project manager is preparing for project closure. The team has learned valua...HardQ29A project manager is leading a software development project where the client has requested frequent demonstrations of...HardQ30A project has the following network diagram with activity durations:<br/><br/>Activity A: 4 days (no predecessors)<br...HardQ31A project manager discovers that a key project artifact (the requirements specification) has not been updated in six ...HardQ32A project team member approaches the project manager with concerns about the ethical implications of a project delive...HardQ33A project manager is working on a government contract that requires specific security clearances for team members. Tw...HardQ34A project manager is leading an agile project where the team has been consistently missing sprint commitments. Analys...HardQ35A project manager is working with a procurement team to select a vendor for a critical project component. Three vendo...HardQ36A project team has identified a risk that a key supplier might not deliver components on time due to their own supply...HardQ37A project manager is leading a team that includes members from different cultural backgrounds. During team meetings, ...HardQ38A project is transitioning from the development phase to the testing phase. The development team has completed their ...HardQ39A project manager notices that team productivity has decreased significantly over the past two weeks. Team members se...HardQ40A project manager is working on a regulatory compliance project where requirements are well-defined and unlikely to c...HardQ41A project team member reports that they are being asked to work overtime frequently to meet project deadlines, but th...HardQ42A project manager is leading a digital transformation project that will change core business processes. Early user fe...HardQ43A project manager is working with a virtual team spread across multiple time zones. Team members report feeling disco...HardQ44A project manager discovers that the project's current trajectory will deliver the technical requirements but may not...HardQ45A project team is using a Scrum framework, and during the sprint retrospective, team members identify that they spend...HardQ46A project manager is leading a team where one member consistently produces high-quality work but struggles with meeti...HardQ47A project manager receives a change request that would add significant value to the project but would require extendi...HardQ48A project manager is working on a software development project using an agile approach. The product owner frequently ...HardQ49A project manager is leading a cross-functional team that includes members from engineering, marketing, and operation...HardQ50A project manager discovers that a critical project issue has been escalated to senior management without their knowl...HardQ51A project team is working on a mobile application development project. During user acceptance testing, users report t...HardQ52A project manager is leading a team that includes both permanent employees and contractors. The contractors have spec...HardQ53A project manager is working on a project where the original business case assumed certain market conditions that hav...HardQ54A project manager is leading a team where two senior team members have a personality conflict that is affecting their...HardQ55A project manager is working on an agile project where the team has been consistently delivering working software eve...HardQ56A project has the following three-point estimates for a critical activity:<br/><br/>Optimistic (O): 8 days<br/>Most L...HardQ57A project manager discovers that a team member has been sharing confidential project information with colleagues outs...HardQ58A project manager is leading a software development project where the client has requested detailed progress reports ...HardQ59A project manager is working with a team that has been together for several months and has developed strong working r...HardQ60A project manager is leading a project that requires compliance with multiple regulatory frameworks. During a complia...HardQ61A project manager is working on a complex integration project involving multiple legacy systems. The technical team r...HardQ62A project manager is leading an agile project where the team has been struggling with estimation accuracy. Sprint aft...HardQ63A project manager is working with a stakeholder who frequently requests detailed status updates and explanations for ...HardQ64A project team has been working effectively together for six months. A new organizational policy requires all team me...HardQ65A project manager is leading a software development project using Scrum methodology. The development team reports tha...HardQ66A project manager discovers that a key team member has been offered a promotion to another department and will be lea...HardQ67A project manager is working on a digital transformation project that involves changing core business processes. User...HardQ68A project manager is leading a team that includes members from different functional departments. Each department has ...HardQ69A project manager is working on a project where the sponsor has been replaced due to organizational restructuring. Th...HardQ70A project team is using Scrum and has been consistently delivering working software each sprint. However, the product...HardQ71A project manager is leading a team where several members are working remotely due to geographic distribution. The re...HardQ72A project manager is working on a project that involves implementing new technology across multiple business units. E...HardQ73A project manager discovers that a critical vendor has been experiencing financial difficulties and may not be able t...HardQ74A project manager is leading a cross-cultural team with members from high-context and low-context cultures. During te...HardQ75A project manager is working on a regulatory compliance project where the regulatory agency has updated their require...HardQ76A project has the following earned value data at the end of month 8:<br/><br/>- Planned Value (PV): $400,000<br/>- Ea...HardQ77A project manager is leading a team that has been working together successfully for eight months. A new team member w...HardQ78A project manager is working on a software development project where the client has requested a demonstration of the ...HardQ79A project manager discovers that two different teams working on related project components have made conflicting tech...HardQ80A project manager is working on a project where the business case was based on achieving specific cost savings throug...HardQ81A project team is using Kanban to manage workflow, and the project manager notices that work items are consistently t...HardQ82A project manager is leading a team that includes both permanent employees and contractors from different companies. ...HardQ83A project manager is working on a compliance project where the regulatory requirements are complex and subject to int...HardQ84A project manager is leading a software development project where the development team has been consistently deliveri...HardQ85A project manager is working with a team member who has excellent technical skills but struggles with communication d...HardQ86A project manager is working on a project that involves multiple external vendors. One vendor has consistently delive...HardQ87A project manager is leading an agile project where the product owner frequently changes story priorities during spri...HardQ88A project manager discovers that a team member has been working excessive overtime hours to meet project deadlines. W...HardQ89A project manager is working on a project where the original scope included integration with a third-party system. Th...HardQ90A project manager is leading a team that has been working effectively together for several months. The organization h...HardQ91A project has the following earned value data:<br/><br/>- Budget at Completion (BAC): $800,000<br/>- Earned Value (EV...HardQ92A project manager is working with a stakeholder who has high influence but low interest in the project. This stakehol...HardQ93A project manager is leading a software development project where the development team reports that they are spending...HardQ94A project manager is working on a project where team members are located in different countries with significant time...HardQ95A project manager discovers that a key project deliverable will not meet the quality standards expected by the client...HardQ96A project manager is leading a team where one member consistently produces excellent individual work but struggles to...HardQ97A project manager is working on a project where the client has requested frequent status updates and progress demonst...HardQ98A project manager is leading a project that requires specialized expertise that is not available within the current t...HardQ99A project manager is working on a project where the team has been using agile methodology successfully for several mo...HardQ100In a multi-cultural project team, a misunderstanding regarding the definition of 'Done' has led to quality issues. Th...Hard