    PracticePMI PMP®PMI PMP Practice Exam 2Question 50
    Hard1 markMultiple Choice
    Task 15: Manage project issuesissue-escalationcommunication-breakdownstakeholder-managementcrisis-management

    PMP · Question 50 · Task 15: Manage project issues

    A project manager discovers that a critical project issue has been escalated to senior management without their knowledge. The issue involves a technical problem that the project team was actively working to resolve. Senior management is now questioning the project manager's competence and demanding immediate explanations. What should the project manager do FIRST?

    Answer options:

    A.

    Investigate who escalated the issue and why it bypassed normal communication channels

    B.

    Immediately provide senior management with a detailed status report on the technical issue

    C.

    Focus on resolving the technical issue to demonstrate competence

    D.

    Schedule a meeting with senior management to defend the project team's actions

    How to approach this question

    When issues are escalated unexpectedly, understanding the escalation path and reasons helps address both the immediate situation and underlying communication problems.

    Full Answer

    A.Investigate who escalated the issue and why it bypassed normal communication channels✓ Correct
    Unexpected escalations indicate communication breakdowns that need to be understood. Investigating the escalation path provides context for addressing both the immediate management concerns and preventing future issues.

    Common mistakes

    Immediately defending actions, focusing only on the technical issue, or providing information without understanding the full context of the escalation.
    Question 49All questionsQuestion 51

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →