PMP · Question 04 · Task 13: Determine appropriate project methodology/methods and practices
A construction company is building a hospital with strict regulatory requirements, detailed architectural plans, and a fixed completion date for the opening. However, the medical equipment selection and interior design can evolve based on staff feedback during construction, and the hospital administration wants to see progress on these elements every month. Which project approach would be MOST appropriate for this scenario?
A construction company is building a hospital with strict regulatory requirements, detailed architectural plans, and a fixed completion date for the opening. However, the medical equipment selection and interior design can evolve based on staff feedback during construction, and the hospital administration wants to see progress on these elements every month. Which project approach would be MOST appropriate for this scenario?
Answer options:
Predictive - The regulatory requirements and fixed completion date require traditional waterfall planning
Agile - The evolving requirements for equipment and design need iterative delivery and stakeholder feedback
Hybrid - Predictive approach for construction with agile elements for equipment and design decisions
Iterative - Multiple development cycles allow for continuous refinement of all project aspects
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
Expert