Hard1 markMultiple Choice
Task 3: Assess and manage risksrisk-managementservant-leadershipagile-methodologyteam-collaboration

PMP · Question 03 · Task 3: Assess and manage risks

During iteration planning for a hybrid software project, the team identifies a new technical risk: the third-party API they planned to integrate may not support the required data volume for peak usage periods. This could impact the current sprint goal and the upcoming release to production. The team estimates this affects 40% of the planned sprint work. Which TWO actions should the project manager take FIRST to address this risk?

Answer options:

A.

Add the risk to the product backlog as a high-priority user story for future sprints

B.

Work with the team to identify alternative APIs or technical solutions immediately

C.

Conduct a spike to assess the API's actual capacity and limitations within the current sprint

D.

Remove the integration from the current sprint scope to avoid risk

E.

Escalate to the product owner for immediate prioritization decision

F.

Document the risk in the risk register and schedule a risk review meeting

How to approach this question

Look for immediate, collaborative actions that both assess the risk (spike) and explore solutions (alternative APIs). Avoid premature escalation or scope changes before assessment.

Full Answer

B,C
In agile environments, risks affecting significant sprint work require immediate collaborative action. Spikes provide data-driven assessment while solution exploration demonstrates servant leadership in removing team blockers.

Common mistakes

Choosing documentation or escalation over immediate collaborative problem-solving, or making scope decisions before proper risk assessment.