Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned-value-managementcost-performanceproject-forecastingcalculations
PMP · Question 05 · Task 5: Plan and manage budget and resources
A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>The project manager needs to calculate the Estimate at Completion (EAC) assuming current cost performance will continue for the remainder of the project. What is the EAC? (Round to the nearest dollar, enter numbers only)
A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>The project manager needs to calculate the Estimate at Completion (EAC) assuming current cost performance will continue for the remainder of the project. What is the EAC? (Round to the nearest dollar, enter numbers only)
How to approach this question
Calculate CPI first (EV/AC), then use EAC = BAC/CPI when assuming current performance continues. CPI = 250,000/280,000 = 0.893, EAC = 500,000/0.893 = 560,000
Full Answer
560000
When current cost variances are typical and expected to continue, EAC = BAC/CPI. CPI = EV/AC = 250,000/280,000 = 0.893. EAC = 500,000/0.893 = 560,000.
Common mistakes
Using EAC = AC + BAC - EV (which assumes no future variances) or forgetting to calculate CPI first, or rounding errors in intermediate calculations.
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ06A project manager notices that a highly skilled team member has become withdrawn over the past tw...Hard
Expert