Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned-value-managementcost-performanceproject-forecastingcalculations

PMP · Question 05 · Task 5: Plan and manage budget and resources

A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>The project manager needs to calculate the Estimate at Completion (EAC) assuming current cost performance will continue for the remainder of the project. What is the EAC? (Round to the nearest dollar, enter numbers only)

How to approach this question

Calculate CPI first (EV/AC), then use EAC = BAC/CPI when assuming current performance continues. CPI = 250,000/280,000 = 0.893, EAC = 500,000/0.893 = 560,000

Full Answer

560000
When current cost variances are typical and expected to continue, EAC = BAC/CPI. CPI = EV/AC = 250,000/280,000 = 0.893. EAC = 500,000/0.893 = 560,000.

Common mistakes

Using EAC = AC + BAC - EV (which assumes no future variances) or forgetting to calculate CPI first, or rounding errors in intermediate calculations.

Practice the full PMI PMP Practice Exam 2

100 questions · hints · full answers · grading

More questions from this exam