Hard1 markMultiple Choice
Task 7: Plan and manage quality of products/deliverablesuser-acceptanceusabilitystakeholder-engagementvalue-delivery

PMP · Question 51 · Task 7: Plan and manage quality of products/deliverables

A project team is working on a mobile application development project. During user acceptance testing, users report that while the application meets all functional requirements, the user interface is confusing and difficult to navigate. The development team argues that they built exactly what was specified in the requirements. What should the project manager do?

Answer options:

A.

Accept the application since it meets all specified functional requirements

B.

Blame the requirements team for not specifying usability requirements clearly

C.

Work with stakeholders to assess the usability issues and determine appropriate responses

D.

Ask the development team to fix the usability issues at no additional cost

How to approach this question

When user feedback indicates problems despite meeting requirements, engage stakeholders to assess the issues and determine appropriate responses that deliver user value.

Full Answer

C.Work with stakeholders to assess the usability issues and determine appropriate responses✓ Correct
C
Project success requires delivering value to users, not just meeting technical requirements. When usability issues arise, stakeholder engagement is needed to assess and address user needs appropriately.

Common mistakes

Accepting deliverables that don't meet user needs, assigning blame, or making unilateral decisions about additional work without stakeholder engagement.

Practice the full PMI PMP Practice Exam 2

100 questions · hints · full answers · grading

More questions from this exam