PMP · Question 52 · Task 6: Build a team
A project manager is leading a team that includes both permanent employees and contractors. The contractors have specialized skills that are critical to the project, but they work for different companies and have varying contract terms. Some contractors can only work part-time, while others have different holiday schedules. Which TWO approaches should the project manager use to build team cohesion?
A project manager is leading a team that includes both permanent employees and contractors. The contractors have specialized skills that are critical to the project, but they work for different companies and have varying contract terms. Some contractors can only work part-time, while others have different holiday schedules. Which TWO approaches should the project manager use to build team cohesion?
Answer options:
Establish common team goals and success criteria that apply to all team members regardless of employment status
Create separate communication channels for employees and contractors
Schedule all team activities during times when permanent employees are available
Develop flexible communication and collaboration practices that accommodate different schedules and availability
Assign contractors to work independently to avoid scheduling conflicts
Require all team members to adopt the same working schedule and availability
How to approach this question
Full Answer
Common mistakes