PMP · Question 53 · Task 3: Evaluate and address external business environment changes for impact on scope
A project manager is working on a project where the original business case assumed certain market conditions that have significantly changed. The project is 60% complete and technically on track, but the changed market conditions mean the expected return on investment will be much lower than originally projected. What should the project manager do?
A project manager is working on a project where the original business case assumed certain market conditions that have significantly changed. The project is 60% complete and technically on track, but the changed market conditions mean the expected return on investment will be much lower than originally projected. What should the project manager do?
Answer options:
Continue the project as planned since it's already 60% complete
Analyze the current business case and present options to stakeholders for decision-making
Modify the project scope to reduce costs and improve the return on investment
Accelerate the project timeline to reduce costs and improve the business case
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
Expert