For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 54
    Hard1 markMultiple Choice
    Task 1: Manage conflictpersonality-conflictconflict-resolutionindividual-perspectivesteam-dynamics

    PMP · Question 54 · Task 1: Manage conflict

    A project manager is leading a team where two senior team members have a personality conflict that is affecting their collaboration on critical project tasks. Both individuals are high performers when working independently, but their conflict is creating tension in team meetings and delaying deliverables that require their joint input. What should the project manager do FIRST?

    Answer options:

    A.

    Separate the two team members and assign them to different work streams

    B.

    Meet with each team member individually to understand their perspectives and the source of the conflict

    C.

    Bring both team members together immediately to resolve the conflict

    D.

    Focus on project deliverables and ignore the personality conflict

    How to approach this question

    Personality conflicts require understanding each person's perspective before attempting resolution. Individual meetings provide safe spaces for honest communication.

    Full Answer

    B.Meet with each team member individually to understand their perspectives and the source of the conflict✓ Correct
    B
    Effective conflict resolution starts with understanding each party's perspective. Individual meetings provide safe spaces for honest communication and help identify the root causes of the conflict.

    Common mistakes

    Avoiding the conflict, forcing immediate joint resolution, or separating team members without addressing the underlying issues.
    Question 53All questionsQuestion 55

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →