PMP · Question 28 · Task 16: Ensure knowledge transfer for project continuity
A project is nearing completion, and the project manager is preparing for project closure. The team has learned valuable lessons about integration challenges that could benefit future projects. However, team members are already being assigned to new projects and have limited time for closure activities. What should the project manager prioritize for knowledge transfer?
A project is nearing completion, and the project manager is preparing for project closure. The team has learned valuable lessons about integration challenges that could benefit future projects. However, team members are already being assigned to new projects and have limited time for closure activities. What should the project manager prioritize for knowledge transfer?
Answer options:
Complete all planned closure documentation before team members are reassigned
Schedule individual interviews with each team member to capture their insights
Facilitate a focused retrospective session to capture key lessons and integration insights
Delegate knowledge capture to team leads who will remain with the organization longer
How to approach this question
Full Answer
Common mistakes